PMIPMP home
  FAQ
  PMP Tutorial
  Mock exam
  Other Certification sites
  About PREPAREPM
  PMP Books
   Tutorial Topics
  Introduction
  Fundamentals
  Integration
  Scope
  Time
  Cost
  Risk
  Quality
  HR
  Communication
  Procurement
  Ethics
   Practice questions
  Mock Exam 1
  Communication
  Cost
  HR
  Introduction
  Quality
  Risk
  Schedule
  Scope
  preparepm: Tutorial Project Cost Management
home | tutorial | Mock Exam

preparepm.com Tutorial - Project Cost Management

This chapter covers key concepts related to Project Cost Management.
  1. The knowledge area of Project Cost Management consists of the following processes -

    Project Cost Processes
    Process Project Phase Key Deliverables
    Cost Estimating Planning Activity Cost Estimates,
    Cost Management Plan
    Cost Budgeting Planning Cost Baseline
    Cost Control Control Cost Estimates (updates),
    Cost baseline (updates)

  2. Alternative identification process identifies other solutions to an identified problem.
  3. Value Analysis approach is used to find more affordable, less costly methods for accomplishing the same task.
  4. The Cost Estimation process takes the following inputs -
    • Enterprise environmental factors
    • Organizational process assets
    • Project scope satement
    • WBS
    • WBS dictionary
    • Project Management plan -
      Schedule Management plan,
      Staffing Management plan,
      Risk register
  5. Depreciation is technique used to compute the estimated value of any object after few years. There are three type of depreciation techniques. These are
    • Straight line depreciation The same amount is deprecated (reduced) from the cost each year.
    • Double-declining balance - In the first year there is a higher deduction in the value - twice the amount of straight line. Each year after that the deduction is 40% less than the previous year.
    • Sum of year depreciation - Lets say the life of an object is five years. The total of one to five is fifteen. In first year we deduce 5/15 from the cost, in second year we deduce 4/15, and so on.
  6. Analogous Estimating is an estimating technique with the following characteristics -
    • Estimates are based on past projects (historical information)
    • It is less accurate when compared to bottom-up estimation
    • It is a top-down approach
    • It takes less time when compared to bottom-up estimation
    • It is a form of an expert judgment
  7. In Parametric Modeling Estimation, you use a mathematical model to make an estimate. It is of two types.
    • Regression Analysis
    • is a mathematical model based upon historical information.
    • Learning Curve model is based upon the principal that the cost per unit decreases as more work gets completed.
  8. Bottom up estimation is same as WBS estimation. It involves estimating each work item and adding the estimates to get the total project estimate.
  9. You can expect five to ten questions related to Earned Value Management. These are generally pretty simple once you have good understanding of the concepts, and remember the formulae. These formulae are explained below.

  10. Planned Value (PV) refers to what the project should be worth at this point in the schedule. It is also referred as BCWS (Budgeted Cost of Work Scheduled).
  11. Earned Value (EV) is the physical work completed to date and the authorized budget for that. It is also referred as BCWP (Budgeted Cost of Work Performed).
  12. Actual Cost (AC) is the actual amount of money spent so far. It is also referred as ACWP (Actual Cost of Work Performed).
  13. Estimate At Completion (EAC) refers to the estimated total cost of the project at completion.
  14. CPI refers to Cost Performance Index. It is defined as
      CPI = EV/AC
    If CPI is less than 1, this means that the project is over budget.
  15. BAC refers to Budget at Completion. It is related to EAC.
      EAC = BAC/CPI
  16. ETC refers to Estimate to Completion. It is defined as
      ETC = EAC - AC
  17. CV refers to Cost Variance. It is defined as
      CV = EV - AC
  18. SV refers to Schedule Variance. It is defined as
      SV = EV - PV
    Negative cost or schedule variance means that project is behind in cost or schedule.
  19. SPI refers to Schedule Performance Index. It is defined as
      SPI = EV/PV
  20. VAC refers to Variance At Completion. It is defined as
      VAC = BAC - EAC
  21. The process of Cost budgeting defines time phased cost estimates for the project. For example, in the first month the project will require $10,000. Cost estimating involves defining cost estimates for tasks. Cost budgeting defines cost estimates across time.
  22. The tools and techniques used for Cost Estimating are -
    • Analogous estimating
    • Determine resource cost rates
    • Bottom-up estimating
    • Parametric estimating
    • Project Management software
    • Vendor bid analysis
    • Reserve analysis
    • Cost of quality
  23. Cost baseline refers to what is expected to be spent on the project. It is usually an S-curve. That is the expenditure is less in the beginning, and the end. The expenditure is maximum during the middle of the project.
  24. The after project costs are called life cycle costs.